Skip to main contentManaged construction support · Mon–Fri coverage Playbook / 6 min readFrom scattered RFIs to a Friday-ready report
A compact project-administration pack that puts aging items, decisions, change exposure, procurement risks, and closeout gaps in one review.
Inside the fileEvery column, exactly as it ships.
Illustrative rows. Replace the categories, ageing thresholds, and escalation owners with your project's own rules.
Columns and sample rows contained in Download report CSV| # | Category | Item id | Description | Status | Responsible party | Date opened | Days open | Next action | Next action date | Decision required | Escalation owner | Impact or notes |
|---|
| 1 | Decision required | SAMPLE-001 | Confirm approved finish selection | Open | Project manager | 2026-07-08 | 6 | Record approved selection | 2026-07-15 | Yes | Project executive | Illustrative row only |
|---|
| 2 | Aging RFI | SAMPLE-RFI-014 | Clarify ceiling detail | Open | Design team | 2026-07-01 | 13 | Follow up through approved channel | 2026-07-15 | No | Project manager | Illustrative row only |
|---|
| 3 | Procurement risk | SAMPLE-PO-008 | Long-lead equipment release | At risk | Project manager | 2026-07-10 | 4 | Confirm release authorization | 2026-07-16 | Yes | Project executive | Illustrative row only |
|---|
| 4 | Closeout gap | SAMPLE-CO-021 | Missing warranty document | Open | Subcontractor | 2026-07-05 | 9 | Request document | 2026-07-17 | No | Project manager | Illustrative row only |
|---|
Scroll the table sideways to see all 12 columns →
How to run it
The structure only works with an owner behind it.
01Choose one reporting cutoff
A Friday pack is only trustworthy when every source log uses the same cutoff and the reader knows what changed after it.
- Set the weekly cutoff
- Name the source logs
- Record the last-updated time
- Separate current facts from pending confirmation
02Lead with decisions
The PM should not have to read every open row to find what needs their authority or escalation.
- Decisions required
- Items beyond the agreed response window
- Potential schedule or procurement impact
- Unpriced or unapproved change exposure
- Missing closeout documents
03Keep ownership visible
Every open item should have a responsible party, next action, and next date. Status without ownership is only a description of delay.
- Responsible party
- Current status
- Days open
- Next action
- Next-action date
- Escalation owner
Ungated downloadTake the file. Keep the authority.
No email gate and no follow-up sequence. The structure is yours to adapt; the decisions it supports stay with your team.
Download report CSV ↓More resources
Other tools for the same operating problem.
Make the handoff visibleA template helps. Ownership makes it work.
Define who updates the artifact, when it is reviewed, what triggers escalation, and who has final authority.